Royal Courts of Justice - 'Black Lift'
Guideline Lift Services Limited were established in 1972 and are one of the leading independent lift companies within the South East of England, with expertise in the installation, modernisation, maintenance and repair of all types of passenger lifts from simplex to 8 car groups.
We successfully tendered for the replacement of the
'Black Lift' within the Royal Courts of Justice, Strand,
London. The Consultant and CDM Coordinator were
the Gerald Honey Partnership, their specification
called for the complete removal of an existing 9
person lift including the existing shaft structure and
enclosure, with the installation of a 13 person lift
within a steel and glazed structure, including all
associated builders and electrical works.

The Royal Courts of Justice were opened in 1882
by Queen Victoria. In 1868 it was decided George
Edmund Street R.A. was to be appointed the sole
architect and it was he that designed the whole
building from its foundations to the varied carvings
and spires, sadly he died prior to its completion.
The building has a grade 1 listing by English Heritage
and therefore extensive discussions were undertaken
by the design team to ensure the lift appearance and
design would be acceptable whilst retaining special
features including the decorative iron works around
the lift entrance (portal) required by grade 1 listing.
No alteration to the existing building fabric was
permitted and the use of diagonal bracing to the
structure had to be avoided in order to provide a
minimalistic structure with laminated glass cladding
thus allowing light into the well and providing a view
of the stone stairwell and balustrade as the original
architect intended.

The structure had to be designed and constructed to
be self supporting with attachment to the shaft front
floor beams only. No fixings or steady bolts to the
stone stairwell or balustrade were permitted.
As this was to be a turnkey project, Guideline Lift
Services were appointed as Principal Contractor
and in conjunction with our specialist subcontractors
Access Technology and Perdan Limited commenced
design and planning for the structure enclosure and
lift installation, which entailed firstly the removal
of the existing installation, protection of the stone
balustrade and staircase and the excavation to
the rear of the shaft to accommodate the revised
shaft size, these works were completed by Perdan
Limited.

The shaft structure not only had to be self supporting but also would have to provide support and loadings for the lift installation, together with the concept design criteria of the specification. This proved to be a challenge but our project team working closely with Access Technology and the design team achieved an aesthetically pleasing design whilst encompassing the engineering design for the lift installation. As the portal was being retained as part of the Grade 1 listing, the structure and lift installation had to be set out from the line of the portal prior to the installation of the structure in order to provide a 900 x 2000 clear opening.
The glass enclosure was designed to be symmetrical with cross members and the entrance fronts, however the wing panels were site measured to provide clean lines to the enclosure as a whole. The lift was installed during normal working hours and for safety reasons the glass enclosure was fitted at night, as the building was mostly empty. The lift installation consisted of LiftStore Ethos Control with full flux vector drive operating at 1.6 m/s with an MF82 SASSI machine. Sematic glass doors with special depth kick plates together with DC door operation. Fixtures were supplied by LiftStore, Windcrest, Stentogate and Memco. Steel work was manufactured by Access Technology and overall responsibility for design, procurement, installation, testing and management was undertaken by Guideline Lift Services all in accordance with the Gerald Honey Partnership Specification, EN81-1 and the Lift Regulations 1997.
Whilst this project was both different, interesting and challenging it was the positive input of all parties to work together to achieve what we believe was a modern and acceptable design, which compliments the original architecture.
Principal Contractor
Guideline Lift Services LimitedDesign Team
Gerald Honey Partnership - Lift Consultants & Construction Design Management Co-ordinatorEC Harris - Project Managers
Purcell Miller Tritton - Historical Building Consultants
Structure and Enclosure Manufacturer and Installer
Access TechnologyAssociated Builders Works
lifts@guideline.co.uk